A pipe can fill a tank in 2\frac{2}{3} hours, and another pipe empties it in 4 hours. If both are opened together, how long will it take to fill the tank?
A pipe can fill a tank in $2\frac{2}{3}$ hours, and another pipe empties it in 4 hours. If both are opened together, how long will it take to fill the tank?
एक पाइप टंकी को $2\frac{2}{3}$घंटे में भर सकता है, और दूसरा पाइप उसे 4 घंटे में खाली कर सकता है। यदि दोनों पाइप एक साथ खोल दिए जाएँ, तो टंकी को भरने में कितना समय लगेगा?
Detailed Solution & Logic
8h/ घंटे
Time taken by filling pipe = $2\frac{2}{3}$ hours
$2\frac{2}{3} = \frac{8}{3}$ hours
Filling rate of pipe A:
$= \frac{1}{8/3} = \frac{3}{8}$ tank per hour
Emptying rate of pipe B:
$= \frac{1}{4}$ tank per hour
Net filling rate when both are opened:
$= \frac{3}{8} - \frac{1}{4}$
$= \frac{3}{8} - \frac{2}{8}$
$= \frac{1}{8}$ tank per hour
Time to fill the tank:
$= \frac{1}{1/8} = 8$ hours
Answer: 8 hours
Similar Practice Questions
Two pipes, M and N, can fill a tank in 10 minutes and 15 minutes,
Two pipes, M and N, can fill a tank in 10 minutes and 15 minutes,...
A cistern has two inlet pipes, A and B, and one outlet pipe, C.
A cistern has two inlet pipes, A and B, and one outlet pipe, C. Pipe...
A pipe can fill a tank in 7 hours. Another pipe can empty the full tank in 21 hours. If both the pipes are opened simultaneously, then how much time (in hours) will it take to fill two-thirds of the tank?
A pipe can fill a tank in 7 hours. Another pipe can empty the full...
Rajeshwar can do a piece of work in 12 days,
Rajeshwar can do a piece of work in 12 days, Vikram in 6 days and...
Pipe A can fill a tank in 5 hours. Pipe B can empty it in 12 hours. If both pipes are opened together, how much time will it take to fill the tank?
Pipe A can fill a tank in 5 hours. Pipe B can empty it in...
A can complete a work in 20 days, while B can complete the same work in 25 days. Both work together for 10 days, and then C alone completes the remaining work in 10 days. In how many days can A, B, and C together complete the same work?
A can complete a work in 20 days, while B can complete the same work...
A company undertakes a project to be completed in 40 days with 80 workers. After 10 days, due to a shortage, only 60 workers remain. How many additional workers must be hired after 20 more days to complete the project on time?
A company undertakes a project to be completed in 40 days with 80 workers. After...